BHP Culvert Remediation Phase 4

Aaro experts were on hand to refurbish a culvert at BHP's Yandi Mine, that if it had collapsed could have been costly to their operations.

Aaro were engaged by BHP to structurally refurbish a three-barrel, DN2700 Corrugated Steel Pipe (CSP) on the MAC Line, near BHP’s Yandi Mine Site.  The culverts had corroded over time and needed to be refurbished to extend their life and avoid replacement.

To refurbish the culverts, Aaro first grout filled the heavily deteriorated sections that had resulted in voids in the culverts.  Then CentriPipe, a Centrifugally Cast Concrete Spray product imported from America under our licensed partnership agreement, was applied to the entire culvert. A total of 157t of CentriPipe was applied to the three culverts.

Aaro were successful in completing the works on-time, on budget and to a high standard.  BHP commended Aaro for their project planning, on site supervision and overall ease to deal with throughout the duration of the project.

$890k

Client

BHP

Location

Yandi, WA

Project Duration

1 month

Project Start

April 2021

Project Finish

May 2021

RelatedProjects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

$530kTropicana Tunnel Strengthening WorksMicrotunnelling
Innovation and safety were key to this multi-plate tunnel construction, allowing the Site to maintain production throughout the project uninterrupted.
Tropicana Gold Mine, WA

Our experts can make your next project a success.

Discover how Aaro could provide you with expert solutions backed by experience.

Get in touch
One group, many services